DREDGING. This winter, Newport completed a $475,000 dredging project to remove 10,000 cubic yards of silt from the north easternmost corner of the inner harbor.
The dredged material was collected on a 140' scow, and transported up to the Providence Harbor contained aquatic disposal (CAD) site. This area will now be navigable, with a uniform depth of 9 feet, enabling the installation of new piers and docks at Perrotti Park this Spring and setting the stage for future expansion along Long Wharf.


HARBOR CENTER. Securing a $713,000 US Fish and Wildlife Boating Infrastructure grant, Newport is planning to develop a new harbor center transient boating facility and in the historic Armory on lower Thames Street.
Proposed Business Plan for Armory Wharf Project
Download the latest version of Adobe Reader
Plans also include increasing dinghy and transient yacht dock capacity at the City-owned Ann Street Pier, located next to the Armory complex.
NEW LANDING PIER/DOCKS AT PERROTTI PARK. Newport is enhancing its capacity to handle ferry, cruise ship and water shuttle traffic with the installation of new piers, docks and a gazebo at Perrotti Park in the main harbor area. This $580,000 project is almost complete.
KING PARK/ROCHAMBEAU SEAWALL. Newport invested $644,000 for this restoration project.
VAN ZANDT PIER. This $305,000 project rebuild this very popular pier in the Point section of Newport.
KING PARK STONE PIER AND LIGHTS. $74,000 worth of repairs to principal boater access in the southern part of Newport Harbor.